Hubbard Construction Takes on a New Type of Project: US 19 is Hubbard’s First Build-Finance Project
June 17th, 2010Estimated Final Contract Amount: $109.5 million
Owner: FDOT
Start Date: November 2009
Projected Completion Date: Summer 2014
Location: Clearwater, Fla
US 19 is Hubbard’s first build-finance project. What makes this project unique is that Hubbard has agreed to finance portions of the project and FDOT will pay the money back in installments.
Project Specs:
A 2.4 mile section of US 19 will be converted to a six lane limited access roadway with two lane frontage roads added northbound and southbound. The contract consists of 190,000 CY of excavation, 450,000 CY of embankment, 42,000 feet of storm drain pipe, 420 drainage structures, five bridges, 65,000 tons of asphalt, extensive water, sewer and other utility relocations, MSE walls, lighting, ITS and signing.