Job Well Done! Hubbard finishes SR 5 (US 1) Rio Mar to Midway Road, St. Lucie County

August 28th, 2009

Estimated Final Contract Amount: 28.5 million
Owner: FDOT
Project Began: May 2, 2009
Projected Completion Date: May 11, 2009

Project Description:
Full reconstruction and widening of a 2.9 mile section of US 1 in St. Lucie County from two through-lanes in each direction plus one bi-directional turn lane to three through lanes in each direction plus dedicated turn lanes.  This project included a new drainage system, pond excavation, signalization for five intersections, signage, landscaping, irrigation, sidewalks, median separators, gravity walls, box culvert extensions, concrete sheetpile, pond liners, existing roadway removal, roadway excavation, stabilization, base and asphalt.

Hubbard Group’s largest stimulus funded project: Tampa International Airport

August 28th, 2009

Contract Amount: $34 million
Owner: Hillsborough County Aviation Authority
Project Began: June 2009
Projected Competition Date: October 2010

Project Description:

Tampa International Airport plans on building a second terminal by 2025. In advance of this development, and with $8 million in funding from the American Recovery and Reinvestment Act, the airport has combined two projects within one contract:

  • The North Terminal Stormwater Improvement Project (bid-build) consists of site development to accommodate the future Terminal development (300,000 CY pond, 8,600 LF of channel excavation, and 4,000 LF of box culvert).
  • The Taxiway B Rehabilitation and Bridge (design-build) consists of the demolition of an existing taxiway, and the reconstruction of an elevated taxiway, including a cast-in-place post-tensioned bridge for aircraft traffic. This project also includes new fuel line construction (double-wall 18/22” pipe), airfield signage and lighting, FAA duct bank work, and a stormwater drainage system.

SR 417 Interchanges at Moss Park and SR 417 and Innovation Way

August 28th, 2009

Moss Park Contract Amount $18.35 million
Owner: The Orlando-Orange County Expressway Authority (OOCEA)
Project Began: June 2008
Projected Completion Date: December 2009

Innovation Way Contract Amount $14.6 million
Owner: OOCEA
Project Began: September 2008
Projected Completion Date: December 2009

There are actually two contracts involved, both being constructed for the Orlando-Orange County Expressway Authority. The projects are immediately adjacent to each other and to the public eye would appear to be the same project. Pile driving operations for both projects were completed in April and earthwork, MSE walls, drainage, roadway, electrical and concrete work is also proceeding according to schedule, as is the toll plaza building construction. The two projects are both currently on target for December 2009 completion.

Hubbard Construction Wins Bid for US 19 in Clearwater

August 28th, 2009

The $103 million project is the largest contract at Hubbard to date. It also is the first Build/finance project at the company.

The 2.4 mile section of heavily traveled/congested six lane urban at-grade roadway is being converted to a six lane limited access roadway with two lane frontage roads being added northbound and southbound. The 1665 day contract consists of 190,000 CY of excavation, 450,000 CY of embankment, 42,000 feet of storm drain pipe, 420 drainage structures, five bridges, 65,000 tons of asphalt,  extensive water, sewer and other utility relocations, MSE walls, lighting, ITS and signing.

Hubbard Works 1 Million Man Hours without a Lost Time Injury

August 28th, 2009

Hubbard Construction Company, for the first time in its history, has worked one million consecutive manhours without a lost-time injury. Congratulations to everyone at Hubbard for this achievement.

Hubbard Group | Hubbard Construction Co. | Blythe Construction | Eurovia |©2007 Hubbard Group