Major Projects: Blythe Construction

June 27th, 2007


 
US-601 Design Build

www.us601widening.com 

Project Owner: NCDOT
Location: Union County, NC
Cost: $54 million

Job particulars: Ten-mile widening design-build project. The need for this project is based on a history of severe crashes on US-601 and a fatality rate higher than the statewide average for similar facilities.


US-311 Project

Project Owner: NCDOT
Location: Guilford and Randolph Counties in NC
Cost: $102 million

Job particulars: The 6.3 mile, $102 million project includes construction of a major interchange at I-85, seven box culverts, 15 new bridge structures and demolition of an existing bridge. It also involves more than three million metric tons of earthwork.


I-85 Rowan County Design-Build
www.i85widening-rowan.com

Project owner: NCDOT
Location: Rowan County, NC
Cost: $65 million
Begin and end date: January 2005 to winter 2007

Job particulars: Widen over three miles of highway as well as utility, bridge and road relocation.


Pedmont-Triad International Airport

Project Owner: Piedmont-Triad Airport Authority
Location: Greensboro, NC
Cost: $20.3 million
Begin and end date: March 2006 to winter 2007

Job particulars: Runway construction, grading and utility work.


Lowes Corporate Campus

Project Owner: Lowes Inc.
Location: Mooresville NC
Cost: $11 million
Begin and end date: January 2007 to December 2008

Job particulars: Mass grading, exterior loop road, helicopter pad, two new office sites, two new parking garages


Hubbard Group | Hubbard Construction Co. | Blythe Construction | Eurovia |©2007 Hubbard Group